Choose File > Options > Schedule. In the Default start time and Default end time boxes, type the times that you want the default work day to start and end. To use the same settings automatically in all future projects, choose All New Projects in the Calendar options list.
Moreover, how do I change the start date on project 365?
Or
- Click Project – Project Information.
- In the Schedule from field, Project Start Date is selected by default.
- In the Start date box, enter the date that you want to schedule from.
Just so, how do you set the start date of the project?
What is the default scheduling mode in MS project?
MS Project doesn’t automatically schedule tasks based on the defined project start date and the duration of each task. This gives you the flexibility to schedule each task at the date you want it to start. By default, MS Project uses manual scheduling.